Department |
Activities detailed with critical process steps and best practises |
Activities having process flowchart & ERP |
Activities not considered for process detailing |
|---|---|---|---|
|
Finance & Legal |
Title Due Diligence Business / Funding Plan Business / Funding Plan aligned to approved Budget |
|
JDA SDA Debt Syndication and CP Compliance Fund Disbursement Short term funding for consultants and excavation during design period |
|
Approvals |
|
|
AAI Mining Approval Low Rise Approval EC, CFE & CFO Approval Final Fire Approval Process Fire & Municipal Approval OC Explosives license for HSD and DGs |
|
Design |
Management Requirements Checklist, Lessons Learnt Excavation Brief Sign-Off |
Design Development MEP Coordinated Tender Package Budget Based on Design Hand over To PMO - Stage 1 (Tender Drawings & Budget) Hand over To PMO - Stage 2- Issue of GFC (Coordinated Structural & MEP) |
Approvals based on stage A sign off Shop Drawing Approval of Structural Steel Traffic Analysis (Preliminary) Master Plan, Block Planning Core Detailing and Concept Completion Liaisoning Pre-Check + Drawings For Fire & Municipal |
|
Contracts |
Feasibility Consultant Appointment Appointment of Soil Test Vendor and SBC Test Appointment of Surveyor and Site Survey Excavation Appointment & Blasting Permission LDC Appointment |
GC Identification Structural Steel NSC Identification Issue of LOA – GC NSC Identification (MEP & Other Packages) GC & NSC Contract Award |
|
|
Execution |
Site Excavation Phase 1 Site Barrication Deliver Strategy & Procurement Strategy Site Excavation Phase 2 post Environmental Approval Site Mobilization |
|
|